BELIZE |
Tourism
Project
Caracol
Access Road Upgrading
Loan No.
1250/OC-BL
The
Government of Belize has received a loan from the Inter-American Development
Bank (IDB) in conjunction with the International Cooperation and Development
Fund (ICDF) to finance the improvement of the tourism infrastructure in Belize.
It is intended that part of the loan proceeds be applied to eligible payments
under:
·
Contract
No. 1: Upgrading of the Caracol access road from Caracol to Ballerina Junction
(approximately BZ$ 8.5 million)
·
Contract
No. 2: Upgrading of the Caracol access road from T junction north of Mai Gate
to the Western Highway junction at Santa Elena (approximately BZ$ 2 million)
·
Contract
No. 3: Upgrading of the Caracol access road from T junction north of Mai Gate
to the Western Highway junction at Georgeville (approximately BZ$ 1.5 million)
The
Government of Belize now invites prequalification applications from contracting
firms wishing to carry out the above-mentioned works. Prequalification is open
to all bidders from eligible source countries. It is expected that invitations
to bid be made in October 2002.
Contractors
are invited to submit comprehensive details of their relevant experience in
undertaking similar projects.
Indicative
quantities for major items are:
·
Contract
No. 1: Gravel paving of existing road 22 feet wide: 445,000 m3; Excavation:
170,000 m3; Pipe culverts: 750 m
·
Contract
No. 2: Gravel paving of existing road 22 feet wide: 30,000 m3; Excavation:
85,000 m3; Pipe culverts: 100m
·
Contract
No. 3: Gravel paving of existing road 22 feet wide: 25,000 m3; Excavation:
12,000 m3; Pipe culverts: 25 m
Contractors
will be allowed to employ approved sub-contractors. Prequalified firms will be
allowed to bid on one, all or any combination of packages based upon their
interest, their capacity and capability.
Evaluation
of construction firms will be based on the following criteria: (i) the judicial
nature and nationality of the bidding firm; (ii) its general background; (iii)
its financial position; (iv) the available equipment and staff; (v) its
relevant experience; (vi) its commitment to ongoing works; and (vii) its
litigation history. The Government of Belize shall not be bound to give any
reason for not prequalifying any applicant and will not defray the costs of
applications.
Prequalification
documents and questionnaires may be obtained at the address below, between 0900
and 1600 hours, Mondays through Fridays, upon payment of a non-refundable fee
of US$ 50 or BZ$ 100. Certified checks, draft money orders or postal orders should
be payable to the Government of Belize.
The
completed prequalification forms and questionnaires must be submitted in
duplicate, enclosed in a sealed envelope clearly marked “Prequalification
Application Document for Caracol Access Road”, to the address below no later
than 1400 hours (local time) on 15 October 2002. Late applications will not be
accepted.
Contact: Ministry of
Works.
Attn: Chief Executive
Officer.
Power Lane.
Belmopan, Belize.
Tel: (501) 822-2131.
Fax: (501) 822-3282.
E-mail: works@btl.net